Yesterday afternoon we synchronized from Pro 39 listings to be launched that evening. Half of them were launched immediately. We reviewed our listings thinking we may have accidently forgot to say delay but it was there.
Why would this happen?
Dennis
posted on October 18, 2004 09:58:14 AM new
Hi Dennis,
To schedule an item properly, you must have selected the schedule option in Pro and filled out both the date field and the time field. Did all of your listings have all these fields filled out?
posted on October 19, 2004 06:03:58 AM new
We went back to review to make sure we had selected the delay button and put in the date and time. we saw that they were all done that way.